AwardedIRLWorks€1,250,000
Dublin City Council Contract for Middle Wad Flood Alleviation Scheme Howth Road Tunnel
- Published
- Published 17 July 2025
- Deadline
- Closed 16 October 2024
Overview
The Contract provides for the Detailed Design and Construction of the following flood alleviation works, which comprises provision of additional capacity along the culverted River Wad: Tunnelled culvert, circa 34m long, 1500mm diameter between no. 96 and no. 97 Howth Road to operate in parallel with existing culvert route. • Circa 5m long culvert connection from tunnelled culvert to existing culvert. • Connection chamber to split flows between new and existing culvert routes. • Drive and reception shafts to facilitate tunnel construction. • Removal and disposal of all surplus materials • At each work area and construction compound: reinstatement and landscaping in accordance with the reinstatement plans. • Temporary works include establishing and securing a main construction compound, which will be in operation for the entire duration of the Works; and temporary works/ set down areas at Howth Road. The main compound is likely to be situated in the green area at the Castle Court estate. • Other temporary works including, but not limited to, temporary river diversion at the Howth Road and stockpiling of excavated earth. • Breaking out existing Wad River to pass through the proposed downstream shaft. • Grouting of temporary diversion at completion of works • Ancillary Works as per the requirements of this specification including, but not limited Howth Road and stockpiling of excavated earth. • Breaking out existing Wad River to pass through the proposed downstream shaft. • Grouting of temporary diversion at completion of works • Ancillary Works as per the requirements of this specification including, but not limited to, pre and post condition surveys, testing works and specialist engagement
Key details
- Country
- IRL
- Status
- Awarded
- Category
- Works
- Estimated value
- €1,250,000
- Procedure
- Open
- Published
- 17 July 2025
- Questions by
- 25 September 2024
- Deadline
- Closed
Construction work for tunnels, shafts and subwaysConstruction work for tunnelsTunnelling worksTunnel linings construction workUnderground work other than tunnels, shafts and subwaysFlood-prevention works
Award outcome
- Awarded value
- €1,776,734
- Award date
- 17 July 2025
Contract ending soon? Skim tracks incumbents and flags recompetes early. Book a demo to set up alerts.
Notice history
Every published notice in this contracting process, newest first.
Contract Award Notice
17 July 2025
Contracting authority
Dublin City Council
Procuring entityDublin, IRL
IE-EPPS-CA: 1253
Authority website ↗
Get the full picture
AI analysis, bid scoring, and expert strategy for this tender
Skim analyses every tender against your company profile and tells you whether to bid, how to win, and who you are up against.
See which competitors are winning the contracts you're chasing.
15-minute call. We'll pull the win data on your real pipeline and show you what Skim does with it.