Skip to content
In deliveryUnited KingdomWorks

Supply and Installation of addition solar PV panel generation system

Published
Published 17 February 2026
Deadline
Closed 27 March 2026

Overview

The University of Salford seeks proposals to supply and install additional PV generation to one of its buildings. The Northern Engineering Robotics Innovation Centre (NERIC) was constructed in 2022 for the University of Salford, the first building on its new Innovation Campus on Frederick Road, M6 6AP. At the time it was fitted out with 15 kWp onto its higher flat roof. The roof was originally designed to accommodate more panels, but these were reduced in a value engineering exercise. 2.0 Goods and Services to be provided The University seeks to double the amount by adding another 15 kWp bringing the total to 30kWp on the existing higher, gravel ballasted flat roof, easily visible from google satellite, while still maintaining access to service plant and the PV system. We can provide hourly data for 2025 for import, generation and export and would want a model worked up using this data as a basis but on double the existing building consumption (c55,000 kWh/yr to 110,000kWh/yr) as we are expecting this to rise very shortly. Modelling should show generation, import, export, costs saved over 20-year period as a minimum, carbon saved using current grid carbon intensity, payback periods etc including inverter replacement at year 10. Work on a current electricity import price of 28p/kWh and a grid (import) carbon intensity of 177g CO2e/kWh and an export price of 5.6p/kWh Can you please provide us with a proposal and quote to include. • A cost/carbon/payback model based on the above parameters. • A rough breakdown of costs in your quote rather than a single figure. • Provide the data sheets for the proposed panels, non-penetrating fixing system and inverters. • The combined panel/fixing weight as kg/m2 as installed on the roof. • State the panel and inverter warranty. If it doesn't already have it, the inverter should have a minimum 10-year warranty. • The generation meter provided or utilising the existing one will need to be linked to our BMS system. • How and where you intend to lift the panels and fixings onto the roof. • Provide a separate option for battery storage, it's price and impact on export. • You would be expected to carry out all the liaison for approvals with the DNO. • Comply with the University's standard T&Cs for this type of electrical work. • Two references with contact details for similar systems you have installed.

Key details

Country
United Kingdom
Status
In delivery
Category
Works
Procedure
Open
SME suitable
Yes
Published
17 February 2026
Questions by
27 March 2026
Deadline
Closed
Classification (CPV)
Solar panel roof-covering work

Award outcome

Awarded value
£20,117
Award date
19 April 2026
Contract period
31 March 2026 → 1 April 2027
Winner
  • DES ENERGY LIMITED

Contract ending soon? Skim tracks incumbents and flags recompetes early. Book a demo to set up alerts.

Notice history

Every published notice in this contracting process, newest first.

  1. Contract

    21 April 2026

    View notice ↗
  2. Contract Notice

    17 February 2026

    View notice ↗

Contracting authority

  • University of Salford

    Buyer

    Salford, United Kingdom

    GB-CHC: RC000666

Get the full picture

AI analysis, bid scoring, and expert strategy for this tender

Skim analyses every tender against your company profile and tells you whether to bid, how to win, and who you are up against.

See which competitors are winning the contracts you're chasing.

15-minute call. We'll pull the win data on your real pipeline and show you what Skim does with it.

Awarded: Supply and Installation of addition solar PV panel generation system — won by DES ENERGY LIMITED — Skim