AwardedZMBWorksUS$38,850,000
Zambia-Tanzania Interconnector Project – Package 1 for second 330 kV single circuit Pensulo-Mpika overhead transmission line, 186km length, and associated substation works at Pensulo and Mpika
- Published
- Published 16 April 2025
- Deadline
- Closed 16 May 2025
Overview
Zambia Electricity Supply Corporation Limited has awarded a contract for Package 1 of the Zambia-Tanzania Interconnector Project, comprising construction of a second 330 kV single circuit overhead transmission line spanning 186 km between Pensulo and Mpika, together with associated substation works at both locations. The project was awarded on 16 July 2026 with an estimated value of USD 38.85 million.
Key details
- Country
- ZMB
- Status
- Awarded
- Category
- Works
- Estimated value
- US$38,850,000
- Procedure
- Open
- Published
- 16 April 2025
- Deadline
- Closed
Public utilities
Award outcome
- Award date
- 16 July 2026
Contract ending soon? Skim tracks incumbents and flags recompetes early. Book a demo to set up alerts.
Notice history
Every published notice in this contracting process, newest first.
Contract Award Notice
16 July 2026
Contract Notice
16 April 2025
Contracting authority
Zambia Electricity Supply Coorporation Limited
BuyerZMB
Get the full picture
AI analysis, bid scoring, and expert strategy for this tender
Skim analyses every tender against your company profile and tells you whether to bid, how to win, and who you are up against.
See which competitors are winning the contracts you're chasing.
15-minute call. We'll pull the win data on your real pipeline and show you what Skim does with it.