AwardedPOLWorksPLN 44,051,094
Modernizacja stacji elektroenergetycznej 110/15 kV RPZ-9 Białystok na terenie działalności PGE Dystrybucja S.A. Oddział Białystok
- Published
- Published 22 October 2025
- Deadline
- Closed 13 February 2026
Overview
PGE Dystrybucja S.A. procured modernization works on the 110/15 kV RPZ-9 electrical substation in Białystok, with the project co-financed by the European Funds for Eastern Poland 2021-2027. The contract was awarded to ELEKTROPAKS Sp. z o.o. on 26 May 2026 for 52,767,000 PLN and has been completed.
Key details
- Country
- POL
- Status
- Awarded
- Category
- Works
- Estimated value
- PLN 44,051,094
- Procedure
- Open
- Published
- 22 October 2025
- Deadline
- Closed
Construction work
Award outcome
- Awarded value
- PLN 52,767,000
- Award date
- 26 May 2026
- Contract period
- — → 24 August 2026
- ELEKTROPAKS Sp. z o.o.
Contract ending soon? Skim tracks incumbents and flags recompetes early. Book a demo to set up alerts.
Notice history
Every published notice in this contracting process, newest first.
Contract Award Notice
2 June 2026
Contract Notice
5 February 2026
Contract Notice
28 January 2026
Contract Notice
16 January 2026
Contract Notice
8 January 2026
Contract Notice
15 December 2025
Contract Notice
9 December 2025
Contract Notice
27 November 2025
Contract Notice
20 November 2025
Contract Notice
22 October 2025
Contracting authority
PGE Dystrybucja S.A.
Procuring entityLublin, POL
Authority website ↗
Get the full picture
AI analysis, bid scoring, and expert strategy for this tender
Skim analyses every tender against your company profile and tells you whether to bid, how to win, and who you are up against.
See which competitors are winning the contracts you're chasing.
15-minute call. We'll pull the win data on your real pipeline and show you what Skim does with it.