AwardedGermanyWorks
Neuerstellung der EMSR-Technik in der Gebläsehalle 2 (GBH 2) auf der Kläranlage Mönchengladbach-Neuwerk
- Published
- Published 26 January 2026
- Deadline
- Closed 1 April 2026
Overview
Niersverband awarded EUR 3,067,808.15 to Vortmann GmbH on 1 June 2026 for the reconstruction of EMSR (instrumentation and control) technology in Blower Hall 2 at the Mönchengladbach-Neuwerk wastewater treatment plant. The work encompasses installation of eight turbine compressors in separate fire compartments, two backup power stations, transformer station 4 with transformers and low-voltage distribution equipment, active harmonic filters, automation systems integrating into the existing PCS 7 control system, and electrical building infrastructure including lighting and outlets. The project ensures redundancy for the biological treatment process and is now complete.
Key details
- Country
- Germany
- Status
- Awarded
- Category
- Works
- Procedure
- Open
- SME suitable
- Yes
- Published
- 26 January 2026
- Deadline
- Closed
TransformersLow- and medium-voltage cableElectrotechnical equipmentOptical-fibre cables for data transmissionData-transmission cableSewage plant equipmentElectrical fitting workLightning-protection works+3 more
Award outcome
- Awarded value
- €3,067,808
- Award date
- 1 June 2026
- Contract period
- 8 June 2026 → 25 February 2027
- Vortmann GmbH
Contract ending soon? Skim tracks incumbents and flags recompetes early. Book a demo to set up alerts.
Notice history
Every published notice in this contracting process, newest first.
Contract Award Notice
4 June 2026
Contract Notice
23 March 2026
Contract Notice
27 February 2026
Contract Notice
2 February 2026
Contract Notice
26 January 2026
Contracting authority
Niersverband
Procuring entityViersen, Germany
Authority website ↗
Get the full picture
AI analysis, bid scoring, and expert strategy for this tender
Skim analyses every tender against your company profile and tells you whether to bid, how to win, and who you are up against.
See which competitors are winning the contracts you're chasing.
15-minute call. We'll pull the win data on your real pipeline and show you what Skim does with it.