In deliveryUnited KingdomWorks£1,592,000
Design and Build Contractor for PSDS3 Decarbonisation Works at Cornerstone Arts Centre, Didcot
- Published
- Published 6 November 2025
- Deadline
- Closed 2 December 2025
Overview
the Works for Option 1 will include: Verification of RIBA4 designs, Removal of the gas-fired boilers and vessels and associated works in the internal plant room. Installation of Air Source Heat Pumps (ASHP) and associated vessels and equipment to provide Heating and Hot Water Services. Removal and Replacement of Air Handling Units and removal of the rooftop chiller. Radiator Replacements. Installation of Solar PV. All associated works and general building de-carbonisation measures.
The Works for Option 2 will involve: Verification of RIBA4 design for Solar PV only. Installation of Solar PV and associated works.
If option 1 is adopted, PSDS funding requires a "whole building" approach to the decarbonisation measures identified for the M&E Services upgrade, including all reasonable steps to reduce heating demand and minimise the total building energy use.
Key details
- Country
- United Kingdom
- Status
- In delivery
- Category
- Works
- Estimated value
- £1,592,000
- Procedure
- Open
- Published
- 6 November 2025
- Questions by
- 24 November 2025
- Deadline
- Closed
Building construction work
Award outcome
- Awarded value
- £1,284,476
- Award date
- 16 March 2026
- Contract period
- 10 February 2026 → 31 August 2026
- ASHE CONSTRUCTION LIMITED
Contract ending soon? Skim tracks incumbents and flags recompetes early. Book a demo to set up alerts.
Notice history
Every published notice in this contracting process, newest first.
Contract
23 March 2026
View notice ↗Contract Notice
6 November 2025
View notice ↗
Contracting authority
South Oxfordshire District Council
BuyerAbingdon, United Kingdom
GB-PPON: PRWZ-2743-VQTG
Get the full picture
AI analysis, bid scoring, and expert strategy for this tender
Skim analyses every tender against your company profile and tells you whether to bid, how to win, and who you are up against.
See which competitors are winning the contracts you're chasing.
15-minute call. We'll pull the win data on your real pipeline and show you what Skim does with it.