Overview
The Heathrow Infrastructure Project (HIP) consists of 3 smaller projects - Harmondsworth Office,
Harmondsworth Switchgear and Colnbrook Switchgear.
Harmondsworth Office consists of the following:
To undertake a fit-out of the Harmondsworth IRC Office Accommodation to create an open-plan
office space with increased desk capacity to meet the operational requirements of the HO.
Wates will be required to produce a developed design proposal which captures the HO's
requirements.
The proposed 2nd floor shall contain:
- 1nr 14-person meeting room/ boardroom
- 1nr prayer room
- 1nr wellbeing/ recovery area
- 78nr task desks in the open plan office
- 5nr breakout areas (1nr privacy setting and 4nr 2-person condo huts)
- 1nr accessible toilet and 4nr gender-neutral toilets
- A new printer hub with storage spaces
- A newly refurbished refreshment hub and seating area for up to 13nr people
Harmondsworth Switchgear consists of the following:
The works comprise the upgrade of electrical infrastructure at Harmondsworth IRC. This intent of
the works is to increase the electrical resilience of the establishment and provide opportunities for
future expansion. Upgrading the resilience of the electrical infrastructure at Harmondsworth IRC
through the provision of a permanent back-up generator plus HV transformer replacement. The
site must stay operational throughout the project through isolating the works.
In summary, the contracted works shall include:
- Removal of the existing transformer 1 and associated HV breaker.
- Provision of a new 1600kVA transformer and associated HV breaker.
- Provision of a new 1250kVA fixed generator complete with enclosure and 12-hour day tank
within the new generator enclosure.
- Replacing the existing generator control panel with a control panel complete with a
changeover switch that accepts 2No. generator connections, one for the existing fixed
generator and one for the new fixed generator. Location to be within the new fixed
generator enclosure and modifications required to main LV Panel.
- Hard wiring the 2No. generators to the new control panel and this control panel back to the
main LV switchboard existing changeover.
- Modifications to existing fence lines to include new generator compound.
Colnbrook Switchgear consists of the following:
The upgrade of electrical infrastructure at Colnbrook IRC.
This intent of the works is to increase the electrical resilience of the establishment and provide
opportunities for future expansion.
Key details
- Country
- United Kingdom
- Status
- Awarded
- Category
- Works
- Estimated value
- £5,636,753
- Procedure
- Selective
- SME suitable
- No
- Published
- 15 May 2026
- Deadline
- Closed
Switchgear
Award outcome
- Awarded value
- £4,750,479
- Award date
- 21 March 2025
- Contract period
- 5 May 2025 → 10 April 2026
- Wates Construction Limited
Contract ending soon? Skim tracks incumbents and flags recompetes early. Book a demo to set up alerts.
Notice history
Every published notice in this contracting process, newest first.
Contract Award Notice
15 May 2026
Contracting authority
Ministry of Justice
BuyerWestminster, United Kingdom
Get the full picture
AI analysis, bid scoring, and expert strategy for this tender
Skim analyses every tender against your company profile and tells you whether to bid, how to win, and who you are up against.
See which competitors are winning the contracts you're chasing.
15-minute call. We'll pull the win data on your real pipeline and show you what Skim does with it.